The reconstruction of the overpass is being completed on the Krasnodar–Yeysk road

0
Озвучить текст
Select important
On
Off

In the Starominsky district of the Krasnodar Territory, the reconstruction of the overpass through the railway, which is located on the Krasnodar–Yeysk highway, is being completed. This is reported by KrasnodarMedia news agency with reference to the regional Ministry of Transport and Road Management.

Work is underway in the area of the village of Starominskaya on the 175th km of the highway. The contractor has already completed the main stages of reconstruction, completed the assembly and sliding of the superstructure, and installed structures on supports.

"Now the builders are actively equipping the approaches to the building. The roadbed is 95% ready, the reinforcement of the roadsides with monolithic concrete and the installation of side stones have been completed in full, the filling and strengthening of the slopes of the cones have been completed," the agency reports.

According to the Ministry of Transport, road workers have also completed the laying of the top layer of pavement, including on the approaches to the overpass. There are no delays from the schedule.

Reconstruction of the overpass on the Krasnodar–Yeysk highway started in April 2025. The work is scheduled to be fully completed at the end of July 2026.