The renovation of the main street has started in St. Petersburg

0
Озвучить текст
Select important
On
Off

In St. Petersburg, on Monday morning, August 4, large-scale repair work began on Nevsky Prospekt. They will last about a month, according to 78.ru .

Workers have already installed cones and brought in special equipment. Until Friday, August 8, they will have to update the Palace Passage.

From August 6 to August 12, specialists will work on tram tracks at the intersection of Nevsky and Liteyny Avenues. Traffic will not be restricted.

From August 13 to August 27, road workers should begin repairing the Nevsky section from Admiralteysky Prospekt to Vosstaniya Square.

Earlier in July, it was reported that the work should be completed within a month — by September 3. The cost of the reconstruction project is estimated at 461 million rubles. The last major renovation of the roadway on the main artery of the city was carried out in 2018.